Creating a new PPM task
Manual Method
Vantify CAFM allows you to create PPMs that will run indefinitely, following a rule you have presented. We also have an importer for creating PPMs in bulk, but sometimes you may need to only create a few lines as opposed to a bulk load. We’d recommend anything less than 5 to do it manually but of course the choice is yours.
Creating a new line is quick and easy and you have more control than with the importer, this guide explains how to create the new PPMs.
IMPORTANT - There are two stages to this process, the second half, generating the PPMs is often overlooked.
Step 1 – Creating the line
Navigate to Tasks – Manage Tasks
And click +Add
The first step is to choose the site and choose the service type:
In Vantify, Service Type – Hard or Soft Service defines whether or not an asset will be required for the task.
For example PAT testing wouldn’t require a specific asset so you can put it down as soft.
NOTE – once a task has been assigned as hard or soft it can’t be changed to the opposite. If it has an asset assigned it will always require an asset, if you haven’t assigned an asset it’ll never require an asset.
Click continue
The next page is split in two
Section 1 – task details
Add a name (100 character)
Description if much more detail is required, but this is optional
Set the service provider who will be attending to this task
After you choose service provider you’ll be able to add an asset, or choose from an existing asset.
Assets
Clicking add new asset will allow you to create a new asset, the minimum you need is name, so populate this and click create:
Tasks Continued...
Ignore Job Group as it is very rarely used
And you can associate a service routine or SFG-20 if available
Finally, set status as active and move to the next section.
Section 2 – Add Frequency
Click Add frequency to be taken to the frequency section
Description – this will supersede the description given in section 1, this is usually left empty.
Document type – if a document type such as certificate or job sheet is required specify that here.
Choose the frequency – weekly, monthly or yearly.
Then the interval. Example – quarterly, (or every 3 months), would have a frequency of monthly and an interval of 3. Every 3 months. Fortnightly would be weekly, 2. Half yearly would be monthly, 6.
After selecting the interval a new field will appear which is prefix, this allows you to set the rule for the frequency.
For example first Monday, second Tuesday etc.
Note the two bottom options:
Last – this allows you to select the last Friday, or more beneficially, the last weekday.
Date – this allows you to set the rule for a specific date such as 13th
Finally, set a statutory type if it is a legal compliance task and click add.
Here’s an example:
This will create a task every 3 months on the last weekday of the month. It is a Gas job and requires a certificate.
Added to the details set in section 1, we can now click create
Step 2 – Generating the PPM
IMPORTANT – this is a step that is often missed, the task has been created and will appear on your planner but will have no dates associated to it.
Navigate to Tasks > Generate planner:
And navigate to your site and find your task. In our example we only have one task so it’s easy to identify.
Tick the box on the left of the task and click generate selected (you could also leave it unticked and generate all filtered, but this has the danger of generating every task on your list, so we’d recommend using ticks and selected)
Start date specifies the date you’d like the task to start running from.
Note, it will honour your rule, so if the rule was last weekday, and you’ve set 1st November as above, it will automatically move it to the last weekday in November.
So long as the date you’ve specified is before the date the first rule will land on, it will work effectively.
End date will specify when the task will run until. Leaving it empty means it will run indefinitely.
Click create
The page will load and you’ll find your tasks have now been generated and will be in Draft status:
And using the end date example, where it runs indefinitely, we’ve changed the filter to 2048 and you’ll see our task is still running:
The final step
The final step is to submit for approval, as our tasks are in draft at the moment. This means you can continue to make tweaks before you submit it.
Once you are ready tick the box again and click send selected for approval.
They’ll change to blue when pending approval:
And green once approved:
Related Guides
Vantify CAFM Support
For further assistance on anything covered in this guide or others, please contact the Vantify admin team on 01480 499740 or helpdesk.cafm@vantify.com.
This guide was created by Vantify's Product Team and reflects the latest updates as of the specified date. Please note that the information provided may evolve with future system updates or changes. Additionally, some details may vary based on your specific user permissions and account settings within Vantify.